Mitel Migration Project Summary Page

This page will inform you which branches have moved to the new Mitel Cloud based server

What is the Project Plan?

 

Branch Current Mitel Version New Hardware has arrived? Call Flow Mapping Porting by Telco? Cloud Client Setup? Aprox. Completion
Columbia Cloud Yes Completed Completed Done
Houston Cloud 1 extra Yes Completed Completed Done
Pembina Cloud 6 extra Yes Legacy Forwarded Completed Done
SweetGrass Cloud 4 extra Yes Legacy Forwarded Completed Done
Portal Cloud Yes Carrier Forwarded Completed Done
Blaine Cloud 5 Spare phones Yes Carrier Forwarded Completed Done
Port Huron/Detroit Cloud Yes Legacy Forwarded Completed Done
Buffalo Cloud Yes Legacy Forwarded Completed Done
Champlain Cloud Yes Carrier Forwarded Completed Done
Seattle Cloud Yes Legacy Forwarded Completed Done
Fort Erie Cloud 1 extra Yes Completed Completed Done
Peninsula Cloud Yes Completed Completed Done
Regina Cloud Yes Completed Completed Done
Calgary Cloud 7 spare phones Yes Completed Completed Done
Coutts Cloud Yes Legacy Completed Done
Ottawa Cloud Yes Legacy Completed Done
Vancouver Cloud Yes Legacy Completed Done
Pac Highway Cloud Yes Legacy Completed Done
St. Johns Cloud Yes Legacy Completed Done
Halifax Cloud Yes Legacy Completed Done
Niagara Cloud Yes Legacy Completed Done
North Portal In Progress No No No May 3 2023
Edmonton In Progress No No No May 4 2023
Winnipeg In Progress No No No May 11 2023
Emerson In Progress No No No Mar 17 2023
DPC In Progress No No No May 17 2023
Thunderbay In Progress No No No Mar 18 2023
Sarnia In Progress No No No May 19 2023
Windsor In Progress No No No May 19 2023
Sault Ste Marie Local No No No May ? 2023
Toronto In Progress No No No May ? 2023
Fort Frances Local No No No May 24 2023
Mirabel Local No No No May 24 2023
Prescott Local No No No May 25 2023
Quebec City Local No No No May 31 2023
Lacolle Local No No No May 31 2023
Montreal Local No No No May 31 2023