Mitel Migration Project Summary Page

This page will inform you which branches have moved to the new Mitel Cloud based server

What is the Project Plan?

 

Branch Current Mitel Version New Hardware has arrived? Call Flow Mapping Porting by Telco? Cloud Client Setup? Aprox. Completion
Columbia Cloud Yes Completed Completed Done
Houston Cloud 1 extra Yes Completed Completed Done
Pembina Cloud 6 extra Yes Completed Completed Done
SweetGrass Cloud 4 extra Yes Completed Completed Done
Portal In Progress 2 extra Yes Completed Completed Nov 29 2022
Blaine In Progress No No No Dec 16 2022
Port Huron/Detroit In Progress No No No Dec 16 2022
Buffalo In Progress No No No Dec 16 2022
Champlain In Progress No No No Dec 16 2022
Seattle In Progress No No No Dec 16 2022
Fort Erie Cloud 1 extra Yes Completed Completed Done
Peninsula Cloud Yes Completed Completed Done
Regina Cloud Yes Completed Completed Done
Calgary Cloud Yes Completed Completed Done
Coutts In Progress No No No Dec 16 2023
Vancouver In Progress No No No Jan 5 2023
Pacific Highway In Progress No No No Jan 13 2023
Ottawa In Progress No No No Jan 5 2023
Joliette In Progress No No No Jan 5 2023
Toronto In Progress No No No Jan 5 2023
Edmonton Local No No No Jan 18 2023
North Portal Local No No No Jan 18 2023
DPC Local No No No Feb 2 2023
Thunderbay Local No No No Feb 2 2023
Winnipeg Local No No No Feb 2 2023
Emerson Local No No No Feb 2 2023
Fort Frances Local No No No Feb 9 2023
Sault Ste Marie Local No No No Feb 9 2023
Prescott Local No No No Feb 9 2023
Niagara Local No No No Feb 16 2023
Windsor Local No No No Feb 16 2023
Montreal Local No No No Feb 16 2023
Sarnia Local No No No Feb 16 2023
Halifax Local No No No Feb 23 2023
Lacolle Local No No No Feb 23 2023
Quebec City Local No No No Feb 23 2023
Mirabel Local No No No Feb 23 2023
St. Johns Local No No No Feb 23 2023